smithery/ethical-ai-syndicate

sprint-planning-facilitator

Use when preparing for or running sprint planning. Use after backlog refined. Produces capacity analysis, story recommendations, dependency mapping, risk flags, and meeting agenda.

Installation

$ npx skills add smithery/ethical-ai-syndicate --skill sprint-planning-facilitator

Similar popular skills

Related neighbors and high-traction skills in the same topics — useful to compare before installing.

Also in this package

Other skills from smithery/ethical-ai-syndicate · top by installs.

npx skills add smithery/ethical-ai-syndicate

Browse all from smithery/ethical-ai-syndicate

More details

Agent compatibility

Declared targets from SKILL.md / docs. Unmarked agents are not listed — the skill may still install via the CLI.

Claude Code Not declared
Cursor Not declared
Codex Not declared
GitHub Copilot Not declared
Windsurf Not declared
Gemini CLI Not declared
Cline Not declared
OpenCode Not declared

Package contents

Files included with this skill beyond the listing page.

  • skill md SKILL.md 7,972 B
  • docs SUMMARY.md 215 B

History

  1. First recorded snapshot · 0 installs

SKILL.md

Sprint Planning Facilitator

Overview

Prepare for and facilitate effective sprint planning sessions. Produces capacity analysis, recommends stories based on priority and capacity, identifies dependencies and risks, and provides structured meeting agendas.

Core principle: Sprint planning should result in a realistic commitment with clear goals—not an overloaded wishlist.

When to Use

  • Preparing for upcoming sprint planning
  • Calculating team capacity after absences factored
  • Selecting stories from refined backlog
  • Identifying cross-team dependencies

Output Format

sprint_planning:
  sprint_number: "[N]"
  sprint_dates:
    start: "[YYYY-MM-DD]"
    end: "[YYYY-MM-DD]"
    working_days: "[N]"
  
  capacity_analysis:
    team_members:
      - name: "[Name]"
        role: "[Role]"
        availability: "[%]"  # 100% = full sprint, 80% = 1 day off, etc.
        notes: "[PTO, training, etc.]"
    
    total_capacity:
      available_person_days: "[N]"
      historical_velocity: "[Points from last 3 sprints]"
      recommended_commitment: "[Points range]"
      capacity_confidence: "[High | Medium | Low]"
  
  sprint_goal:
    primary: "[One sentence goal]"
    success_criteria:
      - "[Measurable outcome 1]"
      - "[Measurable outcome 2]"
  
  recommended_stories:
    committed:
      - id: "[Story ID]"
        title: "[Title]"
        points: "[N]"
        priority: "[P1 | P2 | P3]"
        assignee_suggestion: "[Name or skill needed]"
        dependencies: ["[Dependency if any]"]
        risk_flag: "[None | Low | Medium | High]"
    
    stretch:
      - id: "[Story ID]"
        title: "[Title]"
        points: "[N]"
        condition: "[When to pull in]"
  
  dependencies:
    internal:
      - story: "[Story ID]"
        depends_on: "[Story ID]"
        type: "[Blocks | Informs | Shares-data]"
    
    external:
      - story: "[Story ID]"
        depends_on: "[External team/system]"
        status: "[Confirmed | Pending | At-risk]"
        mitigation: "[If at-risk]"
  
  risks:
    - risk: "[Description]"
      likelihood: "[High | Medium | Low]"
      impact: "[High | Medium | Low]"
      mitigation: "[Plan]"
  
  carryover:
    from_previous_sprint:
      - id: "[Story ID]"
        title: "[Title]"
        remaining_points: "[N]"
        reason: "[Why not completed]"
  
  meeting_agenda:
    pre_planning:
      - "[Preparation item]"
    planning_part_1:  # What to build
      duration: "[Minutes]"
      activities:
        - "[Activity]"
    planning_part_2:  # How to build
      duration: "[Minutes]"
      activities:
        - "[Activity]"

Capacity Calculation

Step 1: Calculate Available Days

sprint_days: 10  # 2-week sprint
team_size: 5

availability:
  - name: "Alice"
    days_off: 0
    available: 10
  - name: "Bob"
    days_off: 2  # PTO
    available: 8
  - name: "Carol"
    days_off: 1  # Training
    available: 9
  - name: "David"
    days_off: 0
    available: 10
  - name: "Eve"
    days_off: 3  # Conference
    available: 7

total_person_days: 44  # vs 50 theoretical max

Step 2: Apply Focus Factor

focus_factor: 0.7  # Account for meetings, support, etc.
effective_capacity: 31  # 44 × 0.7

Step 3: Convert to Points

historical_velocity:
  sprint_n_minus_1: 34
  sprint_n_minus_2: 28
  sprint_n_minus_3: 31
  average: 31

# Adjust for capacity difference
normal_capacity: 35  # person-days in those sprints
this_sprint_capacity: 31
capacity_ratio: 0.89  # 31/35

recommended_commitment: 28  # 31 × 0.89, rounded
commitment_range: "25-30"  # ±10% for uncertainty

Sprint Goal Framework

A good sprint goal is:

Attribute Description Example
Outcome-focused What value delivered, not tasks done "Users can complete checkout" not "Build checkout page"
Measurable Can verify achievement "90% of test users complete flow"
Achievable Realistic given capacity Based on story selection
Singular One primary objective Not "A and B and C"

Sprint Goal Template

By the end of this sprint, [user segment] will be able to [capability]
as measured by [success metric].

Example:

By the end of this sprint, beta users will be able to complete the full onboarding flow as measured by 80% completion rate in testing.

Story Selection Algorithm

Priority Order

  1. Carryover - Finish incomplete work first
  2. Committed dependencies - Unblock other teams
  3. Sprint goal stories - Primary objective
  4. High-value backlog items - Based on priority
  5. Tech debt - Allocate 10-20% capacity
  6. Stretch - If capacity remains

Selection Criteria

include_if:
  - Story is refined (acceptance criteria defined)
  - Story is estimated
  - Dependencies are resolved or scheduled
  - Required skills available this sprint

flag_if:
  - Story larger than 1/3 sprint capacity
  - Story has external dependency
  - Story is first of its type
  - Story touches unfamiliar code

Dependency Mapping

Dependency Types

Type Description Risk Level
Blocks Cannot start until other completes High
Informs Needs information from other Medium
Shares-data Uses same data structures Low

Dependency Visualization

Story A ──blocks──> Story B ──blocks──> Story C
                         │
                         └──informs──> Story D

External: API Team delivery ──blocks──> Story E
          Status: Confirmed for Day 3

Risk Assessment

Common Sprint Risks

Risk Indicators Mitigation
Overcommitment Points > 110% velocity Reduce scope, add stretch
Single point of failure Only one person can do story Pair programming, knowledge share
External dependency Waiting on other team Confirm timing, have backup work
Unknown complexity New technology/domain Spike first, time-box
Carryover debt Multiple sprints of carryover Address root cause

Meeting Agenda Template

Pre-Planning (Before Meeting)

  • Backlog prioritized and refined
  • Capacity calculated
  • Dependencies identified
  • Carryover assessed
  • Sprint goal drafted

Planning Part 1: What (60 min)

  1. Review capacity (5 min) - Present availability, velocity
  2. Propose sprint goal (10 min) - Discuss and refine
  3. Review carryover (10 min) - Remaining work from last sprint
  4. Select stories (25 min) - Walk through recommendations
  5. Confirm commitment (10 min) - Team agreement

Planning Part 2: How (60 min)

  1. Task breakdown (40 min) - Stories → tasks
  2. Identify risks (10 min) - Surface concerns
  3. Assign initial owners (5 min) - Who starts what
  4. Confirm understanding (5 min) - Questions, clarifications

Common Mistakes

Mistake Problem Prevention
Planning to 100% capacity No buffer for unknowns Target 70-80%
Ignoring carryover Compounds sprint-over-sprint Address first
Vague sprint goal No focus, no success measure Use template
Skipping Part 2 Poor task understanding Allocate full time
Not confirming dependencies Blocked mid-sprint Verify before planning

Output Checklist

Before sprint planning is complete:

  • Capacity calculated with availability factored
  • Sprint goal defined and agreed
  • Stories selected within capacity
  • Dependencies mapped and confirmed
  • Risks identified with mitigations
  • Carryover addressed
  • Team has committed (not been committed to)