Create a three-point estimation when the user asks to estimate effort, scope a feature, size work, forecast timeline, or plan capacity for a project or feature

First seen Mar 18, 2026

Installation

$ npx skills add jerelvelarde/chalk-skills --skill create-estimation

Similar popular skills

Related neighbors and high-traction skills in the same topics — useful to compare before installing.

Also in this package

Other skills from jerelvelarde/chalk-skills · top by installs.

npx skills add jerelvelarde/chalk-skills

Browse all from jerelvelarde/chalk-skills

More details

Agent compatibility

Declared targets from SKILL.md / docs. Unmarked agents are not listed — the skill may still install via the CLI.

Claude Code Not declared
Cursor Not declared
Codex Not declared
GitHub Copilot Not declared
Windsurf Not declared
Gemini CLI Not declared
Cline Not declared
OpenCode Not declared

Repository health

Stars 6
License LICENSE
Default branch main
Open issues 1
Status Active

Skill metadata

Parsed from SKILL.md frontmatter.

Version1.0.0
Allowed toolsRead, Glob, Write, Grep

Package contents

Files included with this skill beyond the listing page.

  • skill md SKILL.md 10,046 B
  • docs SUMMARY.md 184 B

History

  1. First seen on skills.sh
  2. First recorded snapshot · 7 installs

SKILL.md

Create Estimation

Overview

Create a structured three-point estimation using PERT-weighted averages. Breaks work into concrete tasks, estimates each with optimistic/likely/pessimistic bounds, identifies risk factors, and produces a total range with a recommended commitment point.

Workflow

  1. Read project context -- Read .chalk/docs/ for PRDs, user stories, acceptance criteria, and architecture docs. Understanding scope and integration points is essential before estimating.
  1. Determine the next estimation number -- List files in .chalk/docs/engineering/ matching the pattern estimation.md. Find the highest number and increment by 1. If none exist, start at 1.
  1. Understand the scope -- From $ARGUMENTS, conversation context, and project docs, identify:

- What exactly is being estimated (feature, epic, spike, migration) - Acceptance criteria or definition of done - Known integration points with existing systems - Whether this is greenfield or modification of existing code - If scope is unclear, ask the user before estimating -- estimation without scope understanding is guessing

  1. Break into tasks -- Decompose the work into concrete, estimatable tasks. Each task should be:

- Small enough to estimate with reasonable confidence (ideally 0.5-3 days of effort) - Independent enough to estimate separately - Inclusive of all work types: implementation, testing, code review, documentation, deployment

  1. Three-point estimate each task -- For every task, provide:

- Optimistic (O): Best case if everything goes smoothly, no surprises, familiar territory - Likely (L): Most probable duration given normal conditions, some minor friction - Pessimistic (P): Worst reasonable case -- unfamiliar code, complex bugs, unclear requirements (not catastrophic, just hard)

  1. Calculate PERT estimate -- For each task: Expected = (O + 4L + P) / 6. Sum all task estimates for the total.
  1. Identify risk factors -- List specific risks that could push the estimate toward the pessimistic end. Assign each a probability (low/medium/high) and impact in time.
  1. Calculate risk buffer -- Add a percentage buffer based on cumulative risk:

- Well-understood work, few unknowns: 10-20% buffer - Some unknowns, moderate integration complexity: 20-40% buffer - Significant unknowns, new technology, complex integrations: 40-70% buffer

  1. Determine recommended commitment -- The number the team should commit to externally. This is the PERT total + risk buffer, rounded to a sensible unit (half-days for small work, days for medium, weeks for large).
  1. Write the file -- Save to .chalk/docs/engineering/<n>estimation<feature_slug>.md.
  1. Confirm -- Tell the user the estimation was created with its path, the recommended commitment, and the confidence range.

Filename Convention

<number>_estimation_<snake_case_feature>.md

Examples:

  • 2estimationuser_authentication.md
  • 5estimationpayment_integration.md
  • 9estimationmigratetov2_api.md

Estimation Format

# Estimation: <Feature or Work Item Title>

Last updated: <YYYY-MM-DD>

## Scope

<Brief description of what is being estimated. Link to PRD or user story if available.
State any scope boundaries explicitly: "This estimate covers X but not Y.">

## Assumptions

- <Assumption 1, e.g., "API contracts are finalized and won't change">
- <Assumption 2, e.g., "Design mockups are complete before development starts">
- <Assumption 3, e.g., "One engineer working full-time on this">

## Task Breakdown

| # | Task | Optimistic | Likely | Pessimistic | PERT Estimate |
|---|------|-----------|--------|-------------|---------------|
| 1 | <Task description> | <O> | <L> | <P> | <(O+4L+P)/6> |
| 2 | <Task description> | <O> | <L> | <P> | <(O+4L+P)/6> |
| 3 | <Task description> | <O> | <L> | <P> | <(O+4L+P)/6> |
| ... | ... | ... | ... | ... | ... |
| | **Subtotal** | **<sum O>** | **<sum L>** | **<sum P>** | **<sum PERT>** |

All values in **engineer-days** unless otherwise noted (1 engineer-day = 1 person working 1 full day).

## Commonly Forgotten Tasks

The following are included in the breakdown above. If any were intentionally excluded, note why.

- [ ] Unit and integration tests
- [ ] Error handling and edge cases
- [ ] Code review iterations (typically 1-2 rounds)
- [ ] Documentation updates (API docs, README, runbook)
- [ ] Migration scripts or data backfill
- [ ] Deployment and rollout (feature flags, staged rollout)
- [ ] Monitoring and alerting setup
- [ ] Performance testing under realistic load

## Risk Factors

| Risk | Probability | Impact | Mitigation |
|------|------------|--------|------------|
| <Specific risk> | Low / Medium / High | +<N> days | <How to reduce likelihood or impact> |
| <Specific risk> | Low / Medium / High | +<N> days | <How to reduce likelihood or impact> |

## Summary

| Metric | Value |
|--------|-------|
| **Optimistic total** | <sum of all O values> |
| **PERT total** | <sum of all PERT values> |
| **Pessimistic total** | <sum of all P values> |
| **Risk buffer** | <X%> (<rationale>) |
| **Recommended commitment** | **<PERT + buffer, rounded>** |
| **Confidence range** | <Optimistic> to <Pessimistic + buffer> |

## Recommended Commitment

**<N> engineer-days** (<approximately N/5 weeks> for a single engineer)

This is the number to communicate externally. It includes the PERT-weighted estimate plus
a <X%> risk buffer for <brief rationale>.

## Revisit Triggers

- Scope changes that add or remove acceptance criteria
- Discovery of unknown integration complexity during implementation
- Actual velocity tracking shows >20% deviation from estimates after first 30% of work

Content Guidelines

Estimation Units

Use engineer-days as the base unit. This measures effort, not calendar time.

  • 1 engineer-day = 1 person working 1 full day
  • To convert to calendar time, divide by the number of engineers and add coordination overhead (typically 10-20% per additional engineer)
  • For very small tasks (< 0.5 days), use hours but convert to days in the summary

Calibrating Optimistic vs. Pessimistic

The spread between O and P reveals confidence level:

O:P Ratio What It Means
1:1.5 Very well understood, done it before
1:2 Mostly understood, some unknowns
1:3 Significant unknowns, unfamiliar territory
1:5+ Too uncertain to estimate -- recommend a spike first

If any single task has a ratio worse than 1:5, flag it as needing a timeboxed investigation spike before estimation is meaningful.

Breaking Down Tasks Well

Good task breakdown follows these rules:

  • Each task has a clear deliverable (not "work on X" but "implement X endpoint with validation")
  • Tasks include the full cost: code + tests + review, not just the coding part
  • Integration tasks are explicit, not hidden inside implementation tasks
  • "Glue work" is accounted for: config changes, environment setup, CI pipeline updates

Setting Risk Buffer

The buffer is not padding -- it is a quantified acknowledgment of uncertainty:

Scenario Suggested Buffer
Mature codebase, well-defined requirements, experienced team 10-20%
Some new technology, requirements mostly stable 20-40%
New codebase or major refactor, evolving requirements 40-70%
Greenfield with unproven technology and unclear requirements 70-100% (or recommend a spike)

Effort vs. Duration

Always clarify the distinction:

  • Effort: Total engineer-days of work (what you estimate)
  • Duration: Calendar time to complete (depends on team size, parallel work, interruptions)
  • Two engineers don't halve the duration -- coordination overhead adds 10-20% per person
  • Context switching between projects adds 20-30% to effective duration

Anti-patterns

  • Single-point estimates: "This will take 5 days" is a guess, not an estimate. Always provide the three-point range. The spread itself is valuable information about uncertainty.
  • Anchoring bias: The first number mentioned becomes the anchor. Break into tasks first, estimate each independently, then sum. Never start with a total and work backward.
  • Not accounting for integration/testing time: Implementation is typically 40-60% of total effort. The rest is testing, integration, review, deployment, and documentation. If your estimate only covers coding, it is 40-60% of the real number.
  • Estimating without understanding scope: If you don't have acceptance criteria or a clear definition of done, you cannot estimate. Push back and get clarity first, or estimate the spike to get clarity.
  • Confusing effort with duration: 10 engineer-days is not "2 weeks." It is 2 weeks for 1 engineer, but could be 1 week for 2 engineers (plus coordination overhead), or 3 weeks for 1 engineer with context switching.
  • Planning fallacy: People consistently underestimate by 30-50%. If the team has historical data, calibrate against it. If not, lean toward the pessimistic end for commitments.
  • Precision theater: Reporting "7.3 engineer-days" implies false precision. Round to the nearest 0.5 for small estimates, nearest whole day for medium, nearest week for large.
  • Estimating in isolation: If the work integrates with systems owned by other teams, account for coordination time, API negotiations, and blocked-waiting time. Cross-team dependencies are the most common source of estimation misses.